CLIENT: SIKH COMMUNITY
LOCATION: CNR SUNNYHOLT RD AND MEURANTS LANE BLACKTOWN SYDNEY NSW
VALUE: $ 6.0 million
COMPLETION: 1995
SERVICES: Construction Management/Structural Engineering
This project was design and construction project where the external walls were full height tilt-up loadbearing concrete walls 18m high. The entrance to the temple was constructed from curved concrete panels spanning 12m constructed on site and erected into place. The temple had a suspended concrete slab internally supported by the concrete walls. The roof structure was designed to support brick or concrete decorative domes.
GFConsultants provided complete development and construction management services as well as the complete structural design including tilt-up wall panels. The client was provided with a very high quality building constructed for a very competitive price in a tight time frame.